By pressing the control switch in the UP
position, lift the load slightly off the ground to
test the load and effect on the outriggers and
vehicle. If there are no indications of problems,
the load can be lifted to the desired height by
continuing to press UP. When the load is at the
desired height, swing the crane slowly over the
desired position.
To lower the load, press the switch DOWN,
making certain there are no obstructions under
the load. Release tension on the hook/sling and
remove the sling from the hook, being careful
not to let it swing out of control.
4-5. STORING THE CRANE
Before leaving the job site, it is necessary to
store the crane. Retract the extension boom by
removing the pin in the lower boom and
positioning the extension boom in its fully
retracted position. Insert the locking pin.
On short base models, the boom tip should be
lowered to the deck and secured in that position.
Tall masts provide a pin hole for storage of the
boom at a -90° position. Remove the boom
angle locking pin and gently lower the boom to a
verticle position. Insert the pin as shown in
Figure D-4.
Attach the hook to the hook hanger bracket as
shown in Figure D-3. Be certain the winch
cable is drawn up firmly and that all loose
objects are stored before driving the carrier
vehicle.
Disconnect the remote control handle cable and
store in the truck cab or other suitable, secure
location.
WARNING
NEVER DRIVE THE VEHICLE UNLESS THE CRANE
IS IN THE STORED POSITION AND SECURED
PROPERLY.
Figure D-1. HOOK SAFETY LATCH